DataStage® Release: 9x
Job Type: Parallel
OS: Unix
I have a job with several stages with the last stage being an Oracle Connector stage. I would like the last stage to run with a different config file than the other stages. I looked into node map constraint but it wasn't of much help. Any ideas?
chulett

Premium Poster


since January 2006

Group memberships:
Premium Members, Inner Circle, Server to Parallel Transition Group

Joined: 12 Nov 2002
Posts: 42998
Location: Denver, CO
Points: 221842

Post Posted: Sat Jul 27, 2019 4:31 pm Reply with quote    Back to top    

Why don't we start with the why of this... what would be different about the configuration for this last stage?

_________________
-craig

I swore that I would love you to the end of time, so now I'm praying for the end of time to hurry up and arrive
'Cause if I gotta spend another minute with you I don't think that I can really survive
Rate this response:  
abc123



Group memberships:
Premium Members

Joined: 25 Aug 2006
Posts: 598

Points: 5344

Post Posted: Mon Jul 29, 2019 11:56 am Reply with quote    Back to top    

Nothing would be different. I am just wondering if just the Oracle Connector stage can be run with a higher number of nodes to improve performance. The SQL takes a long time due to the volume of data and was hoping to improve performance.
Rate this response:  
Not yet rated
UCDI



Group memberships:
Premium Members

Joined: 21 Mar 2016
Posts: 376

Points: 3877

Post Posted: Mon Jul 29, 2019 1:10 pm Reply with quote    Back to top    

if you run into something that cannot be set as a parameter, and there are a very few things that are like this, you can make 2 copies of the parallel job with the different setups and call the one you want dynamically in the sequence job.

that said I can't recall if this is something you can stuff into a parameter or not.

From memory only (I don't do a lot of this kind of tampering) I think you can put these config file names into parameter sets and pick the one you want at the sequence level and pass it down from there. I know we have a couple of jobs where we can pick 1cpu or 4 this way.
Rate this response:  
Not yet rated
chulett

Premium Poster


since January 2006

Group memberships:
Premium Members, Inner Circle, Server to Parallel Transition Group

Joined: 12 Nov 2002
Posts: 42998
Location: Denver, CO
Points: 221842

Post Posted: Mon Jul 29, 2019 9:40 pm Reply with quote    Back to top    

Ah, okay. Perhaps you can handle this on the database side? With possibly a parallel hint or setting a default level of parallelism on the tables involved. Each node would get the portion it has to work on and that work could be further "parallel-ized" by Oracle.

_________________
-craig

I swore that I would love you to the end of time, so now I'm praying for the end of time to hurry up and arrive
'Cause if I gotta spend another minute with you I don't think that I can really survive
Rate this response:  
Not yet rated
chulett

Premium Poster


since January 2006

Group memberships:
Premium Members, Inner Circle, Server to Parallel Transition Group

Joined: 12 Nov 2002
Posts: 42998
Location: Denver, CO
Points: 221842

Post Posted: Mon Jul 29, 2019 9:41 pm Reply with quote    Back to top    

Ah, okay. Perhaps you can handle this on the database side? With possibly a parallel hint or setting a default level of parallelism on the tables involved. Each node would get the portion it has to work on and that work could be further "parallel-ized" by Oracle.

_________________
-craig

I swore that I would love you to the end of time, so now I'm praying for the end of time to hurry up and arrive
'Cause if I gotta spend another minute with you I don't think that I can really survive
Rate this response:  
Not yet rated
ray.wurlod

Premium Poster
Participant

Group memberships:
Premium Members, Inner Circle, Australia Usergroup, Server to Parallel Transition Group

Joined: 23 Oct 2002
Posts: 54534
Location: Sydney, Australia
Points: 295710

Post Posted: Wed Jul 31, 2019 7:21 am Reply with quote    Back to top    

You could run the whole job using a configuration file with the higher number of nodes, but use node pool(s) to constrain the other stages to execute in a smaller subset of those nodes.

_________________
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.
Rate this response:  
Not yet rated
PaulVL



Group memberships:
Premium Members

Joined: 17 Dec 2010
Posts: 1277

Points: 8399

Post Posted: Wed Jul 31, 2019 10:45 am Reply with quote    Back to top    

More is not always better.

Look to see how you are accessing that target Oracle system.

Are you doing updates?
Are you using bulk load?
Is the table truncated before you are loading it?
Is your data pre-sorted based upon the keys of your table?
Any locks on that table during your load time?

Have you spoken to your Oralce DBA to see if runstats/reorg needs to be done on the table so that you don't waste time.

I have seen where the target Database was the bottleneck because it was super busy servicing customer queries at the time of load. So if you put even MORE work on it by upping the parallelism, you could be impacting customers.


=============

I have NEVER seen a need to push out any target Connector stage to it's own APT file.

You'd be repartitioning data left and right if your parallelism changed.

You'd potentially be crossing host names if your APT file pushed it to a different host. (TCP/IP traffic is slower than memory to memory traffic)

Your DataStage admin would slap you if you were running on a grid install and hard coded an APT file just for that stage.
Rate this response:  
Not yet rated
chulett

Premium Poster


since January 2006

Group memberships:
Premium Members, Inner Circle, Server to Parallel Transition Group

Joined: 12 Nov 2002
Posts: 42998
Location: Denver, CO
Points: 221842

Post Posted: Thu Aug 01, 2019 7:58 am Reply with quote    Back to top    

All good points. Wink

Came back here after realizing my simplistic suggestion wasn't really appropriate, guess I was thinking more from a source standpoint than a target. D'oh. I too should have asked about the nature of the target load you are doing - updates versus inserts versus a mixture of the two - and what seems to be the issue / bottleneck. Are you sure the target is being fed fast enough? Have you tried replacing the target Oracle connector with a Sequential file stage to check?

_________________
-craig

I swore that I would love you to the end of time, so now I'm praying for the end of time to hurry up and arrive
'Cause if I gotta spend another minute with you I don't think that I can really survive
Rate this response:  
Not yet rated
Display posts from previous:       

Add To Favorites
View next topic
View previous topic
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum



Powered by phpBB © 2001, 2002 phpBB Group
Theme & Graphics by Daz :: Portal by Smartor
All times are GMT - 6 Hours