I have installed and got working the Operations Console and it is tracking information. However it is doing it for only 2 of 3 projects. One project even though it is running jobs, nothing is being captured in the Operational Console.
Is there a project specific setting I need to setup?
Operations Console not tracking jobs in 1 project out of 3
Moderators: chulett, rschirm, roy
-
- Premium Member
- Posts: 30
- Joined: Thu Jan 16, 2003 2:51 pm
Value of parameter DSODBON in DSODBConfig.cfg controls collection of data for DSODB. The value set in system level DSODBConfig.cfg can be overridden at project level.
Check if the value of DSODBON in Project level configuration is set to 0.
Check if the value of DSODBON in Project level configuration is set to 0.
-
- Premium Member
- Posts: 30
- Joined: Thu Jan 16, 2003 2:51 pm