Auto-purge of jobs not happening correctly

Post by kamalshil »

Hi
We have recently migrated from DS 8.5 to DS 8.7
We have multiple multi-instance jobs running in parallel.

Till now in DS 8.5 we had setting to keep only log older than 2 days. Which was achieved by setting a property in using Administrator - > logs -> older than (days) -> set to 2.

Now we did the same setting in 8.7 but its not deleting the logs older than 2 days. Jobs are in Finished status then also this property is working.

Do we need to re-import or compile whole project to make this changes take place in DS8.7 this property was missed by admin to set and was done after we had executed job for 1 week or are we missing something ?
ray.wurlod
Participant
Posts: 54607
Joined: Wed Oct 23, 2002 10:52 pm
Location: Sydney, Australia
Contact:

Post by ray.wurlod »

There is no change in behaviour. Job logs are purged only if the job finished with a status of DSJS.RUNOK or DSJS.RUNWARN. If the job aborts, the log is not purged.
IBM Software Services Group
Any contribution to this forum is my own opinion and does not necessarily reflect any position that IBM may hold.
qt_ky
Premium Member
Premium Member
Posts: 2895
Joined: Wed Aug 03, 2011 6:16 am
Location: USA

Post by qt_ky »

Yes, due to the timing, the simplest way to have all existing jobs pick up the project level auto-purge setting change would be to export and re-import everything. There are several posts on this topic.
Choose a job you love, and you will never have to work a day in your life. - Confucius